How long does the design process take?

Let’s define the design process
as the period from when the architect is hired until the drawings are submitted for a building permit. This actually includes the design as well as construction drawings. The time it takes is dependant on a number of factors.

Factors that can Impact the Design Process

· Site issues need for variances, land use adjustments, etc.

· Size of project kitchen remodel vs. 10, 000 square ft. house

· Complexity of project one story flat site vs steeply sloped site

· Decision making turn around time

· Accessibility of clients availability for meetings

General Design Time Guide for Project Types

· Small Residential Remodel – 45 days to 90 days/1.5 to 3 months

· Large Remodel – 90 to 150 days / 3 to 4 months
Interior remodel to multiple areas within the house such as kitchen remodel, bathroom remodel with minor changes to other rooms

· Full House Remodel – 120 to 240 days / 4 to 8 months

· Small New House – 120 days to 240 days / 4 to 8 months
1500 square feet to 2500 square feet

· Medium Sized House – 120 days to 300 days / 4 to 10 months
2500 to 3500 square feet

· Large House – 180 days to 360 days / 6 to 12 months
3500 to 5000 square feet

· Very large House – 10 to 16 months